Exactions
NOTE: This summary is very simplified, and is provided for informational purposes. Any questions on this topic should be directed to The Office of the Property Rights Ombudsman.
Exactions are permitted, provided they meet legal standards established to protect constitutional rights. Exactions that do not satisfy those standards are not allowed. All local governments may impose exactions, including local districts which provide utility service.
An exaction may be imposed on a proposed development provided that it meets “rough proportionality” analysis, found in Utah Code sections 10-20-911 (for municipalities), and 17-79-812 (for counties), which is:
- An essential link exists between the exaction and a legitimate governmental interest; and
- Each exaction is roughly proportionate, both in nature and extent, to the impact of the development.
Exactions for water interests as a condition of approval must also meet additional requirements in this statute.
A local government’s ability to enact by ordinance and impose Impact Fees, a form of development exaction, is additionally regulated by the state’s Impact Fees Act, Utah Code Title 11, Chapter 36a.
Please see Impact Fees for more information.
Each exaction must satisfy “rough proportionality” analysis. The local government imposing the exaction has the burden of showing that the exaction meets rough proportionality standards.
Government entities have a legitimate interest in promoting the health, safety, and welfare of the public. Activities that improve or promote public well being are usually considered legitimate interests. These include “traditional” government activities such as roads, parks, water systems, stormwater drainage, sewer systems, etc.
An essential link between an exaction and a legitimate government interest is established if the proposed exaction promotes or advances a public interest. The exaction does not necessarily need to be the most efficient or “best” means of promoting the public interest.
A development’s “impact” is a measure of the increased burden on public services caused by the development.
Rough Proportionality analysis has two aspects: An exaction must be roughly proportionate to the development’s impact, both in nature and extent.
- An exaction is roughly proportionate in nature if the exaction addresses a need created by the development. In other words, the impact may be seen as a problem, and the exaction the solution to that problem.
- An exaction is roughly proportionate in extent if the expense of compliance is roughly equal to the public cost necessary to address or assuage the impact. The costs do not need to be exactly equal, only roughly equivalent.
The Office of the Property Rights Ombudsman can advise property owners who are facing exactions from a government entity. Since exactions are a type of property takings, the Ombudsman is authorized to mediate or arbitrate disputes. In addition, proposed exactions could be analyzed in an Advisory Opinion issued by the Office.